Operations Update – September
Bass Oil Limited (ASX:BAS) is an Australian-listed oil producer that holds a majority interest in eight permits in the Cooper Basin including the 100%
owned Worrior and Padulla oil fields and a 55% interest in a South Sumatra Basin KSO. The Company is debt free and committed to creating value
by leveraging the competitive strengths of its team, operating capability, reputation, and relationships in both Australia and Indonesia.
Highlights
• Total sales revenue for September was A$493,600 net to Bass (USD$325,875)
• Daily oil production for the group averaged 234 bopd for the month, up 3% with total
monthly production of 7,023 barrels
• Total Cooper Basin monthly production was 2,787 barrels with 1,222 barrels sold at an
average oil price of A$104.21 per barrel
• Total Indonesian oil production was 4,236 barrels net to Bass with 4,258 barrels sold at an
average oil price of US$65.20 per barrel
• Production enhancement program completed in early October - increases Indonesian oil
production by 20%
• Vanessa acquisition - regulatory approval expected shortly
• Bass is finalising R&D tax credit claim for the deep coal gas project - to lodge this month
Monthly Production and Sales:
5.22
4.20 4.21 3.98 3.73 4.01 4.15 4.21 4.22 4.10 4.01 4.24
2.93
2.87
3.44 3.66
2.97 2.86 2.62
2.97 3.00
2.72 3.05 2.79
0
1
2
3
4
5
6
7
8
9
Production
(kbbl)
Bass Oil Monthly Production (kbbl)
Indonesian Production Cooper Basin Production
ASX Announcement
2
Daily oil production for the group averaged 234 bopd (Bass share) in September, up 2.8%. Monthly
production totaled 7,023 barrels (Bass share) with monthly sales of 5,480 barrels. Total sales revenue for
September was A$493,600 (or US$325,875) net to Bass. See below for further information.
Cooper Basin Operations
Production from the Company’s 100% owned Worrior and Padulla oilfields was 2,787 barrels for September,
averaging 93 bopd, down slightly in August. A rain event in early September interrupted oil sales with only
1,222 barrels exported and sold for the month. Production was not impacted resulting in an increase of 1,300
barrels of oil inventories in the field. The roads reopened early October and stock levels are now reducing to
normal levels. The Company achieved an average oil sales price of A$104.21 per barrel.
Production Operations
Both the Worrior and Padulla facilities both recorded uptimes of over 99% for September.
Gas Appraisal
Vanessa Gas Field (Bass acquiring 100%)
The Company is well advanced in negotiations with gas buyers interested in production from the re-start of
the Vanessa field. Bass is also close to securing the relevant regulatory approvals for the transaction.
The Vanessa gas field acquisition (Figure 1) includes a gas processing facility and a 5-kilometre pipeline
connecting to the Cooper Basin gas transmission network. Detailed planning for the certification and
recommissioning of the Vanessa well, facilities and pipeline has commenced. The Vanessa acquisition is
important to the Company as it provides the opportunity for:
• First gas sales - The recertification and recommissioning the Vanessa gas production facility and
pipeline would enable the Company’s first gas sales into the east coast gas market.
• Reserve growth - By proving up significant untested conventional and tight gas potential in both the
Toolachee and Patchawarra formations that can be accessed from the well by fracture stimulation.
• The advancement of activities to commercialise the deep coals - The Vanessa well penetrated the
entire Permian sequence of sediments, including the deep coals. Bass considers this location ideally
situated to test the commercialisation potential of the large deep coal resource in PEL 182 without
incurring the cost of drilling a dedicated well.
Figure 1: Map of Bass permit PEL 182 displaying Vanessa gas field
3
PEL 182 Deep Coal Commercialisation Study – Phase 2 (Bass 100%)
Bass and SLB have finalised the scope of phase 2 of the study which SLB will lead. In phase 1 the
geomechanical model built by SLB used the Vanessa 1 well as the ‘type well’ for the study. The study will
focus on well and fracture stimulation design for economic exploitation of this significant resource.
The Santos led Cooper Basin JV is focusing its efforts to commercialize this resource in 2025. Santos is
planning to drill two wells in this 12-month period to trial the use of high angle/horizontal well technology
along with multi-stage fracking to deliver a commercial production pilot. The first of these wells will spud
early this quarter and is scheduled for completion and fracture stimulation before year end. Success from
this program will be directly applicable to Bass’ commercialisation efforts.
Triassic Gas Study/Kiwi 1 Field Development (Bass 100%)
The Company has commenced the mapping phase of a study aimed at identifying follow-up opportunities to
the Kiwi gas discovery. The team has already identified at least two additional gas prospects south of the Kiwi
gas field that enhance the Kiwi South stratigraphic trapping potential of the play. The Company will provide a
separate update on this work shortly.
The study includes the reprocessing of the Dundinna 3D seismic survey to improve the imaging of the target
hydrocarbon reservoirs.
Bass continues to pursue funding options, including a farm down, for the Kiwi gas field development.
Figure 2: Map of Bass’ Kiwi Gas Field – Northern Cooper Basin Triassic Gas and Oil Play
4
Indonesian Operations
Production from the Company’s Tangai-Sukananti Oil fields in Indonesia averaged 141 bopd (Bass share) in
September. Bass’ share of field production for the month was 4,236 barrels of oil with 4,258 barrels of oil
sold. The average monthly oil price for September was US$65.20 per barrel.
Production Enhancement
Bass’ Indonesian team has completed a three well production enhancement program aimed at achieving a
material increase in oil production from both the Bunian and Tangai fields.
The program has resulted in an increase in field production of some 20% with the final well, Tangai 5 still
cleaning up.
Development
The final materials required for the drilling of the Bunian 6 oil development well, being the well casing and
tubing, have been delivered to site. As previously reported, Pertamina advised that there is no slot available
on their drilling program to drill the well. Bass is currently evaluating responses from a tender issued for
drilling services. The Company will advise the timing of drilling when a rig has been secured.
Figure 3: Bunian and Tangai Fields Location map
Corporate
The Company is preparing to lodge a Research & Development claim for work carried out in FY24 to commer-
cialise the significant gas resource known to be contained in the deep coals within the Bass’ 100% owned PEL
182. If successful, the Company will receive a 43.5% cash rebate of all qualifying expenditure.
This announcement has been authorised for release by the Board of Directors of Bass Oil Limited.
For further information please contact:
Tino Guglielmo
Managing Director
Bass Oil Limited
Ph: +61 3 9927 3000
Email: tino.guglielmo@bassoil.com.au
Share your feedback
Discover