Operations Update – January
Bass Oil Limited (ASX:BAS) is an Australian-listed oil producer that holds a majority interest in eight permits in the Cooper Basin including the 100%
owned Worrior and Padulla oil fields and a 55% interest in an Indonesian KSO. Bass is debt free and committed to creating shareholder value
Highlights
• Total sales revenue for January was A$471,374 net to Bass
• Daily oil production for the group averaged 237 bopd for the month, with total monthly
production of 7,342 barrels
• Total Cooper Basin monthly production was 2,746 barrels with 1,973 barrels sold at an
average oil price of A$98.86 per barrel
• Total Indonesian oil production was 4,596 barrels net to Bass, with 4,538 barrels sold at an
average oil price of US$63.01 per barrel
• Vanessa acquisition – regulator advised it will approve the transaction
• The South Australian Government advised Bass that it was successful in securing $3.5 million
of grant funding to assist with and accelerate the Kiwi gas field development
Monthly Production and Sales:
Daily oil production for the group averaged 237 bopd (Bass share) in January. Monthly production totaled
7,342 barrels (Bass share) with monthly sales of 6,511 barrels. Total sales revenue for January was
A$471,374 net to Bass. See below for further information.
3.73 4.01 4.15 4.21 4.22 4.10 4.01 4.24
4.78 4.93 4.69 4.60
2.97
2.86 2.62
2.97 3.00
2.72 3.05 2.79
2.78 2.55 2.72 2.75
0
1
2
3
4
5
6
7
8
Production
(kbbl)
Bass Oil Monthly Production (kbbl)
Indonesian Production Cooper Basin Production
ASX Announcement
2
Cooper Basin Operations
Production from the Company’s 100% owned Worrior and Padulla oilfields was 2,746 barrels for January,
averaging 89 bopd, consistent with December. Oil sales totaled 1,973 barrels for the month. The Company
achieved an average oil sales price of A$98.86 per barrel up 5% on December.
Production Operations
The Worrior and Padulla facilities recorded uptimes of 99% for January.
Gas Appraisal
Vanessa Gas Field (Bass acquiring 100%)
During the month, the regulator advised that it would approve the Vanessa transaction. The regulator further
advised that it would shortly issue a letter confirming.
The Vanessa gas field acquisition (Figure 1) includes a gas processing facility and a 5-kilometre pipeline
connecting to the Cooper Basin gas pipeline network. Detailed planning for the certification and
recommissioning of the Vanessa well, facilities and pipeline continues. The Vanessa acquisition provides Bass
the opportunity for:
• First gas sales - Recommissioning of the Vanessa gas production facility and pipeline will enable the
Company’s first gas sales into the east coast gas market in the second half 2026.
• Reserve growth - By proving up the untested conventional and tight gas potential in the Toolachee
and Patchawarra formations. These can be accessed in the existing well by fracture stimulation.
• Advancement of activities to commercialise the deep coals - The Vanessa well penetrated the entire
Permian sequence of sediments, including the deep coals. This location is ideally located to test the
potential of the large deep coal resource in PEL 182 without the cost burden of drilling a well.
Figure 1: Map of Bass permit PEL 182 displaying Vanessa gas field
3
PEL 182 Deep Coal Commercialisation Study – Phase 2 (Bass 100%)
The scope of phase 2 of the study which SLB will lead has been finalised. The study will focus on well and
fracture stimulation design for economic exploitation of this significant resource utilising the Vanessa well
and will commence following completion of the acquisition.
The Santos led Cooper Basin JV is continuing efforts to commercialize this resource. Santos is planning to drill
two wells in this 12-month period to trial the use of high angle/horizontal well technology along with multi-
stage fracking to deliver a commercial production pilot. The first deep coal appraisal well, Jack Lake 8, has
been successfully drilled and fracture stimulated. The well is currently on test. Success in this program will
be directly applicable to Bass’ commercialisation efforts.
Triassic Gas Study/Kiwi 1 Field Development (Bass 100%)
Bass was recently advised that was successful in securing $3.5 million of grant funding from the South
Australian Government to assist with and accelerate the Kiwi field development. The Company continues to
pursue funding options for the balance of project funding, including a farm down, for the Kiwi project.
The Company released an update on the findings of the Triassic gas study in December.1
Bass identified at
least two additional gas prospects south of the Kiwi gas field that enhance the Kiwi South stratigraphic
trapping potential of the play.
In addition, there is a growing body of evidence that is suggesting that there is a new source for the
hydrocarbons discovered at Kiwi and adjacent fields. These hydrocarbons appear to have been generated
from carbonaceous Triassic aged sediments in the Arrabury Trough.2
The study continues and will include the reprocessing of the Dundinna 3D seismic survey to improve the
imaging of the target hydrocarbon reservoirs.
Figure 2: Map of Bass’ Kiwi Gas Field – Northern Cooper Basin Triassic Gas and Oil Play
1
Triassic gas study identifies further potential in Kiwi area – ASX Release 1 December 2025
2
A new Triassic source rock in the Cooper Basin, Australia? – Sharon Tiainen, South Australian Department for Energy
and Mining – First published AEG Conference Perth 8–11 September 2025
4
Indonesian Operations
Production from the Company’s Tangai-Sukananti Oil fields in Indonesia averaged 148 bopd (Bass share) in
January down 2% on December due to minor downtime and natural field decline. Bass’ share of field
production for the month was 4,596 barrels of oil with 4,538 barrels of oil sold. The average monthly oil price
for January was US$63.01 per barrel.
Development
All materials required for the drilling of the Bunian 6 oil development well have been delivered to site. The
team has completed the tender evaluation for the provision of drilling services and has made a
recommendation to PEP which is awaiting approval. The Company will advise the timing of drilling when the
contract has been awarded, and the rig has been secured.
Figure 3: Bunian and Tangai Fields Location map
This announcement has been authorised for release by the Board of Directors of Bass Oil Limited.
For further information please contact:
Tino Guglielmo
Managing Director
Bass Oil Limited
Ph: +61 3 9927 3000
Email: tino.guglielmo@bassoil.com.au