Release date: 15 June 2026
Operations Update – May
Bass Oil Limited (ASX:BAS) is an Australian-listed oil producer that holds a majority interest in fourteen permits in the Cooper Basin including the
100% owned Worrior and Padulla oil fields and a 55% interest in an Indonesian KSO. Bass is debt free and committed to creating shareholder value
Highlights
• Total sales revenue for May was A$735,630 net to Bass
• Cooper Basin oil production was 2,508 barrels with 2,156 barrels sold in the month at an
average oil price of A$149.87 per barrel
• Indonesian oil production was 4,281 barrels net to Bass, with 4,244 barrels sold at an
average oil price of US$101.30 per barrel
• Daily oil production for the group averaged 219 bopd for the month, with total monthly
production of 6,789 barrels up 5%
• Bunian 6 oil development well commenced drilling 5 June after the rig successfully
completed pre-spud safety and compliance checks
• Vanessa transaction: the regulator is finalising the transfer documentation
• Interpretation of the reprocessed Kiwi 3D seismic dataset showing encouraging results
Monthly Production and Sales:
4.22 4.10 4.01 4.24
4.78 4.93 4.69 4.60
3.96 4.27 4.02 4.28
3.00
2.72 3.05 2.79
2.78 2.55 2.72 2.75
2.19 1.76 2.25
2.51
0
1
2
3
4
5
6
7
8
Production
(kbbl)
Bass Oil Monthly Production (kbbl)
Indonesian Production Cooper Basin Production
ASX Announcement
2
Daily oil production for the group averaged 219 bopd (Bass share) in May, up 5%. Monthly production totaled
6,789 barrels (Bass share) with monthly sales of 6,400 barrels. Total sales revenue for May was A$735,630
net to Bass. See below for further information.
Cooper Basin Operations
Production from the Company’s Cooper Basin oilfields was 2,508 barrels for May, averaging 81 bopd, up 8%
on April levels after Padulla returned to production and cleaned up to normal levels. Production from the
two fields is expected to stabilise at between 85 bopd to 90 bopd. Cooper Basin sales were 2,156 barrels at
an average oil price of A$149.87.
Production Operations
The Worrior and Padulla facilities recorded uptimes of 96% and 99% respectively.
Gas Appraisal
Vanessa Gas Field (Bass acquiring 100%)
The final documentation to affect the transfer of ownership is being prepared for approval from the Ministers
delegate. GPA Engineering is progressing the engineering study to firm up the scope for the project to
recommission the facility and return the field to production.
The Vanessa gas field acquisition (Figure 2) includes a gas processing facility and a 5-kilometre pipeline
connecting to the Cooper Basin gas pipeline network. The acquisition provides Bass the opportunity for:
• First gas sales - Recommissioning of the Vanessa gas production facility and pipeline will enable the
Company’s first gas sales into the east coast gas market which is estimated by year end.
• Reserve growth - By booking remaining conventional gas reserves as well as proving up the untested
conventional and tight gas potential in the Toolachee and Patchawarra formations. These can be
accessed in the existing well by fracture stimulation.
• Advancement of activities to commercialise the deep coals - The Vanessa well penetrated the entire
Permian sequence of sediments, including the deep coals. This location is ideally located to test the
potential of the large deep coal resource in PEL 182 without the cost burden of drilling a well.
Figure 2: Map of Bass permit PEL 182 displaying Vanessa gas field
3
PEL 182 Deep Coal Commercialisation Study – Phase 2 (Bass 100%)
The Santos led Cooper Basin JV is continuing efforts to commercialize this resource. Santos is planning to drill
two wells in this 12-month period to trial the use of high angle/horizontal well technology along with multi-
stage fracking to deliver a commercial production pilot. The first deep coal appraisal well, Jack Lake 8, has
been successfully drilled and fracture stimulated. Success in this program will be directly applicable to Bass’
commercialisation efforts.
Kiwi 1 Field Development (Bass 100%)
GPA Engineering is updating the pre-FEED study. Various tie-in options for Kiwi are being discussed with
Santos prior to selecting the concept for the field development FEED study. The FEED study is a critical
element towards a Final Investment Decision.
The South Australian Government and Bass executed the Deed of Grant in May to give effect to the $3.5
million of grant funding to assist with and accelerate the Kiwi field development.
Triassic Gas Study Kiwi Trend (Bass 100%)
The reprocessing of the Dundinna 3D seismic survey is almost complete. The objective of this work is to
improve the imaging of the target hydrocarbon reservoirs. Mapping of the area utilising the reprocessed
data set has begun and is yielding encouraging initial results.
Bass considers that the source of the hydrocarbons discovered at Kiwi were generated from carbonaceous
Triassic aged sediments in the Arrabury Trough1
(Figure 3). Bass has shipped samples of Kiwi condensate as
well as rock samples from wells in the Arrabury Trough to a specialist geochemistry lab in the US for detailed
analyses. This study is expected to provide an improved understanding of the source of the liquids rich gas
discovered at Kiwi and will inform future exploration potential in the surrounding area.
Figure 3: Map of Bass’ Kiwi Gas Field – Northern Cooper Basin Triassic Gas and Oil Play
1
A new Triassic source rock in the Cooper Basin, Australia? – Sharon Tiainen, South Australian Department for Energy
and Mining – First published AEG Conference Perth 8–11 September 2025
4
Indonesian Operations
Production from the Company’s Tangai-Sukananti Oil fields in Indonesia averaged 138 bopd (Bass share) in
May, up 3%. Bass’ share of field production for the month was 4,281 barrels of oil with 4,244 barrels of oil
sold. The average oil price for May was US$101.30 per barrel down 9% on the previous month.
Development
Drilling operations at the Bunian 6 location started 5 June after successful completion of the safety and
compliance checks on the rig and associated equipment. The well is expected to come online in early July
and is expected to double group oil production.
Figure 4: Bunian Wellsite’
Figure 5: Bunian and Tangai Fields Location map
This announcement has been authorised for release by the Board of Directors of Bass Oil Limited.
For further information please contact:
Tino Guglielmo
Managing Director
Bass Oil Limited
Ph: +61 3 9927 3000
Email: tino.guglielmo@bassoil.com.au
Share your feedback
Discover