Operations Update - October 2024
Released
Released
Announcement PDF
ASX Announcement
Release date: 21 November 2024
Operations Update – October
Bass Oil Limited (ASX:BAS) is an Australian-listed oil producer that holds a majority interest in eight permits in the Cooper Basin including the 100%
owned Worrior and Padulla oil fields and a 55% interest in a South Sumatra Basin KSO. The Company is debt free and committed to creating value
by leveraging the competitive strengths of its team, operating capability, reputation, and relationships in both Australia and Indonesia.
Highlights
• Total sales revenue for October was US$455,195 net to Bass (A$692,944)
• Daily oil production for the group averaged 263 bopd for the month and total monthly
production was 8,156 barrels
• Total Cooper Basin monthly production was 2,934 barrels produced and 2,206 barrels sold
at an average oil price of A$113.09 per barrel
• Total Indonesian oil production of 5,222 barrels net to Bass with 5,244 barrels sold at an
average oil price of US$71.22 per barrel
• Kiwi – The pressure survey was completed and the gauges retrieved from the well - the data
interpretation has commenced
• PEL 182 Deep coal study – Bass and SLB have finalised the scope of phase 2 of the study
aimed at identifying the most efficient pathway to commercialisation
Monthly Production and Sales:
Bass Oil Monthly Production (kbbl)
12
Production (kbbl)
10
8
3.16
3.23
3.31
3.01
3.33
3.20
6
3.03
2.95
3.07
2.93
3.02
2.80
4
6.80
2
7.96
6.19
5.46
3.60
4.41
4.64
4.71
4.92
5.91
0
Indonesian Production
Bass Oil Limited
ACN: 008 694 817
Level 5, 11-19 Bank Pl.,
Melbourne 3000
Victoria, Australia
Cooper Basin Production
T + 61 3 9927 3000
F + 61 3 9614 6533
admin@bassoil.com.au
www.bassoil.com.au
6.72
5.22
Daily oil production for the group averaged 263 bopd (Bass share) in October. Monthly production totaled
8,156 barrels (Bass share) with monthly sales of 7,450 barrels. Total sales revenue for October was
US$455,195 (or A$692,944) net to Bass. See below for further information.
Cooper Basin Operations
Production from the Company’s 100% owned Worrior and Padulla oilfields was 2,934 barrels for the month
of October. Oil sales totaled 2,206 barrels for the month. Production averaged 95 bopd in October.
The Company achieved an average sales price of A$113.09 per barrel for oil sales up 2.8% on September.
Cash receipts for oil sales are expected before month end.
Production Operations
There was little unplanned downtime at the Worrior or Padulla facilities in October with both locations
recording an uptime of 97.7% and 99.5% respectively.
The field was operating with one HPS in service in October while a scheduled major overhaul of the engine
on the second unit was completed. The second HPS returned to service in early November. Field production
is expected to increase by ~6% as a result.
Gas Appraisal
Kiwi 1 Extended Production Test (EPT) (Bass 100%)
Bass completed the production test of the Kiwi 1 well in August with the well shut in to commence the
pressure build up phase of the test. The build up survey was completed in October and the pressure gauges
retrieved. The initial results of the pressure build up indicate little to no measurable pressure decline during
the test. The technical team will now perform a pressure transient analysis to confirm reservoir parameters.
The EPT over the Triassic Callamurra formation achieved a maximum flow rate of 4.1 million standard cubic
feet per day on a 48/64” choke setting along with 988 barrels of condensate per day with a flowing wellhead
pressure of 1585 psig. The gas is low in inerts and very liquids rich, yielding over 230 barrels of condensate
per million standard cubic feet.
The result of the EPT has confirmed Bass’ view that Kiwi has significant economic value. For further details
please refer to the ASX release dated 8 November 2024.
Figure 1: Kiwi 1 Wellsite post EPT
Bass is currently assessing the time to first production. Work has commenced towards achieving an FID for
the project. This includes commercial agreements for transportation, processing and sale of gas and
condensate. The Company will build upon the previously completed engineering scoping study to tie the
well into the Cooper Basin gas gathering system.
2
To bring the asset into full production the Company is actively looking at off balance sheet financing initiatives
to accelerate the time to first production and are to enhance shareholder value.
The Company is currently examining the merits of commencing early sales of condensate on a longer duration
EPT whilst fast tracking the deployment of gas sales infrastructure.
PEL 182 Deep Coal Commercialisation Study (Bass 100%)
On 16 September 2024 the Company released a summary of the results of the geomechanical study
completed by SLB to the ASX. The study provided a detailed geomechanical model calibrated with formation
integrity and rock strength data obtained from wells drilled by Santos adjacent to the study area.
Bass and SLB have finalised the scope of phase 2 of the study which will again be led by SLB. The objective
for the next phase of the study is to utilise the MEM to determine preliminary well designs and the number
of frac stages required to achieve an economic flow rate and gas recovery per well to economically exploit
this resource.
Indonesian Operations
Production from the Company’s Tangai-Sukananti Oil fields in Indonesia averaged 168 bopd (Bass share) in
October 2024. Bass share of field production for the month was 5,222 barrels of oil with 5,244 barrels of oil
sold. The average monthly oil price for October was US$71.22 per barrel.
During the month the Bunian 5 well was taken offline with a suspected pump failure.
Development
The subsurface team in Jakarta has reprocessed the 3D seismic data set and the interpretation of the data
set is supporting the potential of a westerly extension of the main Bunian structure. The information gained
from the drilling of the Bunian 6 well will provide valuable data with which to calibrate the interpretation and
inform the decision to drill a the Bunian West feature.
Procurement and planning continued for the drilling of the Bunian 6 development well, south-west of the
prolific Bunian 3 well, see map below.
Well pad construction has been completed and the flowline laid to the edge of the location. The well pad has
been constructed to accommodate at least two wells which will shorten lead times for future drilling
considerably. Bass is currently confirming drilling rig availability to lock in a spud date.
Figure 2: Bunian 6 Well pad
3
This announcement has been authorised for release by the Board of Directors of Bass Oil Limited.
For further information please contact:
Tino Guglielmo
Managing Director
Bass Oil Limited
Ph: +61 3 9927 3000
Email: tino.guglielmo@bassoil.com.au
4