Operations Update - September 2024
Released
Released
Announcement PDF
ASX Announcement
Release date: 17 October 2024
Operations Update – September
Bass Oil Limited (ASX:BAS) is an Australian-listed oil producer that holds a majority interest in eight permits in the Cooper Basin including the 100%
owned Worrior and Padulla oil fields and a 55% interest in a South Sumatra Basin KSO. The Company is debt free and committed to creating value
by leveraging the competitive strengths of its team, operating capability, reputation, and relationships in both Australia and Indonesia.
Highlights
• Total sales revenue for September was US$490,958 net to Bass (A$708,248)
• Daily oil production for the group averaged 324 bopd for the month and total monthly
production was 9,731 barrels
• Total Cooper Basin monthly production was 3,008 barrels produced and 2,367 barrels sold
at an average oil price of A$109.94 per barrel
• Total Indonesian oil production of 6,723 barrels net to Bass with 6,693 barrels sold at an
average oil price of US$70.76 per barrel
• Kiwi 1 – Bass is examining early production options to commence condensate sales as well
as options to accelerate the permanent connection of the well to commence gas sales
• PEL 182 Deep Coal Study – SLB completed the geomechanical model – Bass and SLB finalising
the scope of the phase 2 study aimed at identifying most economic commercialisation plan
Monthly Production and Sales:
Bass Oil Monthly Production (kbbl)
14
Production (kbbl)
12
10
3.82
3.16
3.23
8
3.31
3.01
3.33
3.20
6
3.03
2.95
3.07
3.02
2.80
4
7.72
2
6.80
7.96
6.19
5.46
3.60
4.41
4.64
4.71
4.92
5.91
0
Indonesian Production
Bass Oil Limited
ACN: 008 694 817
Level 5, 11-19 Bank Pl.,
Melbourne 3000
Victoria, Australia
Cooper Basin Production
T + 61 3 9927 3000
F + 61 3 9614 6533
admin@bassoil.com.au
www.bassoil.com.au
6.72
Daily oil production for the group averaged 324 bopd (Bass share) in September. Monthly production totaled
9,731 barrels (Bass share) with monthly sales of 9,060 barrels. Total sales revenue for September was
US$490,958 (or A$708,248) net to Bass. See below for further information.
Cooper Basin Operations
Production from the Company’s 100% owned Worrior and Padulla oilfields was 3,008 barrels for the month
of September. Oil sales totaled 2,367 barrels for the month. Production averaged 100 bopd in September.
The Company achieved an average sales price of A$109.94 per barrel for oil sales. Cash receipts for oil sales
are expected before month end.
Production Operations
There was little unplanned downtime at the Worrior or Padulla facilities in September with both locations
recording an uptime of 96.9% and 99.1% respectively.
The field is operating with one HPS in service while the engine on the second unit undergoes a scheduled
major overhaul. The second HPS is expected to be returned to service in November. Field production is
expected to increase by ~6% as a result.
Gas Appraisal
Kiwi 1 Extended Production Test (EPT) (Bass 100%)
The Company completed the production test of the Kiwi 1 well in August. The well is currently shut in on
build up phase of the test. The pressure gauges downhole will be recovered this month. This will allow the
technical team to perform a pressure transient analysis to confirm the reservoir pressures at the beginning
and end of the test providing a guide to the gas reserves accessed by this well.
The EPT over the Triassic Callamurra formation achieved a maximum flow rate of 4.1 million standard cubic
feet per day on a 48/64” choke setting along with 988 barrels of condensate per day with a flowing wellhead
pressure of 1585 psig. The gas is low in inerts and very liquids rich, yielding over 230 barrels of condensate
per million standard cubic feet, much greater than expected.
There were over 800 barrels of condensate produced during the test which is stored in tanks onsite. The
team is currently arranging for the transportation and sale of this product.
Bass is currently investigating options to bring the well online in an early production mode and accelerate
the permanent tie in of the well to existing production infrastructure.
The result of the EPT has reinforced the view that Kiwi has significant economic value to Bass. For further
details please refer to the ASX releases dated 27 August and 2 September 2024.
Figure 1: Kiwi 1 Wellsite post EPT
2
PEL 182 Deep Coal Commercialisation Study (Bass 100%)
As per the Company’s ASX announcement on 18 May 2024, the geomechanical study being undertaken by
technology leader SLB was completed with a summary of the results contained in the ASX release dated 16
September 2024.
SLB completed the geomechanical model calibrated with formation integrity and rock strength data obtained
from wells drilled by Santos adjacent to the study area. The proprietary data provided by Santos was
provided under a Data Sharing Agreement with Bass in return for Santos accessing the completed model and
results of the study.
The study confirmed a number of key well and frac design parameters, including:
-
The safe mud weight window to be used while drilling to avoid excessive hole ovalisation and
possible wellbore collapse in the coal and/or sandstone sequences.
-
The direction and magnitude of the principal horizontal stresses (SHmax and Shmin) which are key
inputs into wellbore and frac design.
-
Possible solutions to challenges common in horizontal drilling of coal seams, with the MEM indicating that the wellbore be landed in the layers adjacent to the coal sequences to increase the
probability of a successful outcome.
-
Significant areal stress variations exist across the Patchawarra Trough. The PEL 182 area is in a
favourable stress regime.
-
Quantifying the vertical stress profile in the Permian section, a key input into detailed fracture
stimulation design to optimise the number of frac stages placed. The number of stages is a key
parameter influencing the economic outcome from the well.
Bass and SLB are working together to finalise the scope of phase 2 of the study which will again be led by
SLB. The objective for the next phase of the study is to utilise the MEM to determine preliminary well designs and the number of frac stages required to achieve an economic flow rate and gas recovery per well to
economically exploit this resource.
Indonesian Operations
Production from the Company’s Tangai-Sukananti Oil fields in Indonesia averaged 224 bopd (Bass share) in
September 2024. Bass share of field production for the month was 6,723 barrels of oil with 6,693 barrels of
oil sold. The average monthly oil price for September was US$70.76 per barrel.
There was no unscheduled field downtime with all wells on-line.
Development
The subsurface team in Jakarta has reprocessed the 3D seismic data set and the initial interpretation of the
new data set is supporting the potential of a westerly extension of the main Bunian structure. The
interpretation effort is continuing.
Procurement and planning continued for the drilling of the Bunian 6 development well, south-west of the
prolific Bunian 3 well, see map below.
Well pad construction has been completed and the flowline laid to the edge of the location. The well pad has
been constructed to accommodate at least two wells which will shorten lead times for future drilling
considerably. Bass is currently confirming drilling rig availability to lock in an anticipated spud date.
3
Figure 2: Bunian 6 Well pad
This announcement has been authorised for release by the Board of Directors of Bass Oil Limited.
For further information please contact:
Tino Guglielmo
Managing Director
Bass Oil Limited
Ph: +61 3 9927 3000
Email: tino.guglielmo@bassoil.com.au