Bunian 6 Weekly Progress Report
Summary
Bunian 6 – Present depth is 1257 metres - at 0600 hours 14 August, the rig was repairing the hydraulic system for top drive drilling unit
During the week, the 9-5/8” intermediate casing string was run in the hole and cemented in place. The casing hanger, wellhead section and BOP’s were installed and tested successfully. The rig then made up and ran in hole with the drilling assembly
This coming week the plan is to complete repairs to the top drive system and commence drilling the 8-1/2” production hole