Bunian 6 Weekly Progress Report
Summary
Bunian 6 – Present depth is 1257 metres - at 0600 hours 7 August, the rig was running in hole with the 9-5/8” intermediate casing
During the week, the well was drilled to 1257 metres, the setting depth for the intermediate casing string
This coming week the plan is to cement the intermediate casing in place and commence drilling the 8-1/2” production hole
The well, once completed, is expected to boost Indonesian oil production from 250 bopd to 750 bopd (100% share) coming online in late August - Bass is Operator and 55% interest holder in the permit