Bunian 6 Weekly Progress Report
Released
Latest announcements
Announcement summary
Bunian 6 Weekly Progress Report
Bunian 6 – Present depth is 895 metres - at 0600 hours 3 July, the rig was running in hole following a wiper trip, to drill the remainder of the 12-1/4” hole section to ~1400 metres
During the week, the well was drilled from 403 metres to 895 metres
This coming week, the rig will continue to drill the 12-1/4” hole section to ~1400 metres prior to running and setting the 9-5/8” intermediate casing